Production Line Balancer
Assign task times across stations, spot overloaded stations, and quantify line efficiency and balance delay.
ManufacturingOperationsPlanning
Inputs
Balance work across stations.
Line efficiency
26.7%
Balance delay
73.3%
Idle time / cycle
220 sec
Minimum stations
2
Idle labor cost / cycle hr
$1.71
Total task time
80 sec
Station 1
68 sec load
Cut & prep: 18 sec
Assembly: 24 sec
Fasten: 16 sec
Inspection: 10 sec
Station 2
12 sec load
Pack: 12 sec
Station 3
0 sec load
No tasks assigned
Station 4
0 sec load
No tasks assigned